Installation requirements
Standards
The installation of the Worcester Greenstore Ground Source Heat Pump system must be carried out in accordance with the relevant requirements for safety, current Wiring Regulations, local Building Regulations, Building Standards (Scotland), (Consolidation) Regulations and Bylaws of the local water company and Health and Safety document No. 63S (Electricity at Work Regulations 1989). It should be in accordance with the relevant recommendations of the following British Standards and Regulations:
- BS EN 255 — replaced by BS EN 14511
- BS EN 814
- BS EN 378
- The Health and Safety at Work Act 1974
- The Management of Health and Safety at Work Regulations 1999
- The Construction (Health, Safety and Welfare) Regulations 1996
- The Construction (Design and Management) Regulations 1994
- The Lifting Operations and Lifting Equipment Regulations 1998, and any other relevant regulations in force at this time.
- The manufacturer’s notes must not be taken in any way as overriding statutory regulations.
Connecting the heat pump to the heating system
Care should be taken to avoid excessive use of flux on copper pipe connections to minimise the amount of debris that the filter can come into contact with.
System flushing and care
Central heating systems must be power flushed before the heat pump is installed. The system should be prepared in accordance with the guidelines of BS 7593 : 2006.
The filter on the primary circuit should be checked during the first week of operation to ensure that any debris is removed.
Insulation
All pipework from and to the collector (which is not active collector) must be insulated especially when there is less than 0.8m separation between the pipes. Insulation which is to be buried must be robust enough to withstand the weight of the earth above it.
All pipework running to and from the collectors inside the property must also be insulated to a distance of at least 3m from the property. It is recommended that insulation is done prior to clipping pipes to walls to ensure complete coverage.
In some instances on pipework and exposed fittings, condensation may form which should be accounted for when choosing to site the product.
Suitable insulation is available from:
Armacell UK Ltd, Mars Street Oldham Lancashire. OL9 6LY.
Tel: 0161 287 7100