Greenskies Solar-Lifestyle installation guide
Greenskies Solar-Lifestyle panel installation guide
Panel dimensions and clearances

Please observe the following minimum space requirements
Dimension a
Either formula can be used. the lower value can be applied.
Dimensions A and B
(See table below)
Dimension C
At least 2 rows of tiles to ridge the chimney (or at least 0.5m if 3 rows of tiles are smaller than the distance).
Dimension D
At least 0.5m for the flow on the right or left of the collector array.
Dimension E
Equals 1.8m (horizontal version:1.0m) and is the minimum clearance from the upper edge of the collector to the lower profile rail, which is installed first.
Dimension F
If an air vent valve is required in the roof, at least 0.4m for the flow.